OFFICIAL OPENING OF THE NEW ALFRED STEET BRIDGE!

Date: 25/06/2024

We are pleased to share the City of Parramatta’s announcement of the official opening of the new Alfred Street Bridge in NSW, Australia🎉

AUSTRALIA’S 1ST TRUE DIAGONAL ARCH BRIDGE

Opened in November 2023, Alfred Street Bridge is Australia’s first true diagonal arch bridge! It features Teufelberger-Redaelli Full Locked Coil (FLC) structural steel cables supporting the suspended walkway from the bridges arch, and stainless steel balustrading comprising Flexi-Mesh and hamma wire rope and fittings.

OUR INVOLVEMENT

Having worked on the project since 2022, we were engaged by Abergeldie Complex Infrastructure to deliver Full Locked Coil structural steel cables to support the suspended walkway from the bridges arch, and the mesh infill panels to be applied within a stainless steel balustrade system.

FLC STRUCUTRAL CABLES

As Teufelberger-Redaelli’s Australasian distributor we supplied the Full Locked Coil (FLC) cables which were installed by Teufelberger-Redaelli’s expert team.

STAINLESS STEEL BALUSTRADE

On reviewing the initial design criteria for the mesh infill panels to be applied within a mild steel balustrade, we proposed a total stainless steel solution to deliver improvements in sustainability, maintenance, return on investment and solve the issue of dissimilar metals when attaching stainless steel to mild steel (eliminating the need for isolation). The stainless steel alternative also provided a more aesthetically appealing finish.

Our proposed stainless steel solution was accepted, resulting in the stunning balustrade now in place which features hamma® 6mm 1×19 stainless steel cable, hamma® standoffs and Flexi-Mesh.

Our approved Flexi-Mesh installer Bespoke Wire and Rope Pty Ltd installed the balustrade.

TECHNICAL DETAILS

For the technically minded, this project required us to deliver:

  • 320m of FLC structural steel cables from Teufelberger-Redaelli;
  • Over 430m2 of Flexi-Mesh (for the mesh infill panels);
  • More than 1km of hamma® X wire rope, 700 bespoke fittings; and
  • 262 stanchions which included: 14.145 Stainless Steel Total Tonnage (plate for stanchions & CHS),
  • 470m Tonne Lineal Metres of Hand Rail, and 445m Lineal Metres of Bike Rail.

THANK YOU
With over 59 years’ experience in the industry, our teams are involved in many new bridge projects across Australia. Our thanks to the City of Parramatta and Abergeldie Complex Infrastructure for the opportunity to work together on delivering the new Alfred Street Bridge.For more information contact our project team Josh Sheedy and Shaun Salmon.

CONTACT US TODAY

For more information or to discuss how Arcus Wire Group can assist with your next project, please contact our Architectural Sales Team on 1800 272 879 or projects@arcuswire.com

Call Now.... Email Now...

Acknowledgement of Country

In the spirit of reconciliation, Arcus Wire Group acknowledges the Traditional Custodians of Country throughout Australia and their connections to land, sea and community. We pay our respect to their Elder’s past and present and extend that respect to all Aboriginal and Torres Strait Islander peoples today.